Cost Estimate of Grey Structure Construction

Cost Estimate of Grey Structure Construction

 

 

Cost Estimate of Grey Structure Construction

CategoryDetailsCost (PKR)
ExcavationPer cubic foot20-30
FoundationConcrete, rebar, labor (per sq. ft)300-500
Brickwork45,000-50,000 bricks for 5 marla540,000-750,000
Bricklaying LaborPer sq. ft18-20
Cement500-600 bags525,000-720,000
Concrete (Slabs & Beams)Per cubic foot120-150
Steel Reinforcement2.5-3 tons575,000-810,000
RoofingConcrete slab, 1,500 sq. ft450,000-600,000
GravelPer cubic foot60-80
SandPer cubic foot50-70
Plumbing PipesBasic setup30,000-50,000
Electrical ConduitsBasic setup40,000-60,000
WaterproofingMembrane treatment20,000-40,000
Labor CostsBricklaying, steel fixing, etc.450,000-600,000
MiscellaneousScaffolding, waste disposal, etc.50,000-100,000

 

Cost Estimate of Grey Structure Construction in Lahore

Constructing a grey structure in Lahore requires proper planning, careful cost management practices, and an intelligent cost analysis. Here, we divide the reported expenses of each grey structure building project into different categories. Note that these may be liable to change according to the quality of material, skill level, site conditions, and market trend; however, this guide gives you a rough estimate of what to expect.

1. Foundation and Excavation Costs

  • Excavation: Generally, the excavation cost for a general residential property is around PKR 20-30 per cubic foot. The usage of special equipment is likely if the site has problems with soil type, access, and groundwater. This might increase the cost.
  • Foundation: A sound and solid foundation is essential for a building’s stability. This usually includes concrete, steel rebar, and labor and costs about PKR 300-500 per square foot, depending on soil conditions and load requirements.

2. Brickwork

  • Bricks: The brick prices in Lahore are not fixed. On average, high-quality bricks cost PKR 18-19 per brick. A typical 5-marla house requires 45,000-50,000 bricks, which cost 540,000-750,000 in total.
  • Bricklaying Labor: A skilled worker’s square foot of bricklaying costs around PKR 18-20. The complexity of the brickwork and the structure’s size are key factors in the total labor costs, which start from PKR 150,000-200,000.

3. Cement and Concrete Work

  • Cement: Cement is now priced at PKR 1,050-1,200 for 50 kg a bag. The house’s basic structure is about 500-600 bags, costing between PKR 525,000-720,000.
  • Concrete (for Slabs and Beams): A cubic foot of concrete for slabs, beams, and columns costs PKR 120-150 each. Depending on the building design and specifications, the total cost for the average grey structure is PKR 200,000-300,000.

4. Steel Reinforcement

  • Steel supports the structure, particularly in areas at optimum risk to earthquakes, such as Lahore. The charges go up and down. However, the average price is usually around PKR 230-270 per kg.
  • A typical 5-marla house needs nearly 2.5-3 tons of steel. The lowest and highest prices for the steel reinforcement in the grey structure are between PKR 575,000 and 810,000.

5. Roofing (Concrete Slab)

  • Concrete Roofing: Concrete roofing expenditures include work, cement, gravel, sand, and reinforcement steel, costing about PKR 300-400 per square foot. For a standard 5-marla home with a roof area of around 1,500 square feet, roofing costs around PKR 450,000-600,000.

6. Gravel and Sand

  • Gravel: Good-quality gravel is essential to strengthen concrete mixes. The rate of gravel is almost PKR 60-80 per cubic foot.
  • Sand: Fine sand is the only requirement for bricklaying and plastering. Prices of sand are from PKR 50-70 per cubic foot, which would imply a total demand of 1,500 cum at the cost of the order of PKR 75,000-105,000.

7. Plumbing and Electrical Conduits

  • Plumbing Pipes: You should expect to pay between PKR 30,000 and 50,000 for basic plumbing pipes. The price includes the purchase of the main water supply and drainage pipes and the labor cost of the installer. However, it excludes fixtures.
  • Electrical Conduits: Setting up electrical conduits for the wiring (excluding fixtures) typically costs about PKR 40,000-60,000.

8. Waterproofing and Damp Proofing

Moreover, Waterproofing is essential to the foundation and walls to protect them in flood-prone and high-water table areas. A range of PKR 20,000-40,000 is the standard cost for one-time typical membrane treatment and basic 5-marla homes foundation waterproofing.

9. Labor Costs

Labor costs, which are a significant part of the budget, consist of the expense for bricklaying, the pouring of concrete, the steel fixing, and overhead general construction works. Labor costs thence are about PKR 450,000-600,000 for the average house. Skilled labor is a bit more expensive, but it is worth investing in for a good reason.

10. Miscellaneous Costs

Other costs related to scaffolding, temporary site facilities, and waste disposal typically vary from PKR 50,000 to 100,000. However, the total expenses will depend on the site’s preparedness and the construction method.

Total Costs for Grey Structure Construction in Lahore

The raw materials, labor, and other requisites for a 5-marla house can cost as low as PKR 2.5 million and as high as PKR 3.5 million. Material introduction, extensive design, or the use of the best raw materials will likely increase the project’s value.

Conclusion

Construction of a grey structure in Lahore depends on several determinants, like the type of material you choose and the quality of labor. The most reliable technique, in this case, is the appropriate selection of the correct components, with the aim of successfully partnering with labor for verified preparation of the project. Both family housing and business properties being built are interconnected with the cost, which must be carefully addressed for a project to be completed within the budget.

FAQs:

1. What is the average cost for constructing a grey structure in Lahore?

  • The cost for constructing a grey structure in Lahore for a typical 5-marla house can range from PKR 2.5 million to PKR 3.5 million, depending on the choice of materials, design complexity, and labor quality.

2. How much does excavation cost for grey structure construction?

  • Excavation costs typically range from PKR 20-30 per cubic foot. However, the cost may increase depending on soil conditions and the need for special equipment.

3. What is the price of bricks for a 5-marla house?

  • A 5-marla house requires approximately 45,000-50,000 bricks, which can cost between PKR 540,000 to PKR 750,000 depending on the quality and market rates.

4. How much cement is required for a grey structure in Lahore?

  • For a basic 5-marla house, 500-600 bags of cement are needed, costing between PKR 525,000 and PKR 720,000 depending on the cement’s brand and quality.

5. What is the cost of steel reinforcement for the structure?

  • A typical 5-marla house requires 2.5-3 tons of steel, with costs ranging from PKR 575,000 to PKR 810,000 based on the price per kg, which typically ranges from PKR 230-270.

6. How much does roofing cost for a grey structure?

  • Concrete roofing costs around PKR 450,000 to PKR 600,000 for a standard 5-marla home, including the labor, material, and steel reinforcement required for the roof.

7. What are the costs of plumbing and electrical conduits?

  • Basic plumbing setup costs between PKR 30,000 to PKR 50,000, while electrical conduit installation typically costs between PKR 40,000 to PKR 60,000 for a 5-marla house.

8. What additional costs should I plan for in grey structure construction?

  • Additional costs may include waterproofing (PKR 20,000 to PKR 40,000), miscellaneous items like scaffolding and waste disposal (PKR 50,000 to PKR 100,000), and labor costs for various construction activities (PKR 450,000 to PKR 600,000).